Sterlite Grid commissions 1500-crore Jabalpur Transmission Project
Largest private investment in transmission sector; to help 5,000 Mw power supply
)
The estimated cost of the project is Rs 1,500 crore and it would facilitate evacuation of 5,000 Mw (megawatt) of power in north and west transmission corridor. The company said the Dharamjaygarh-Jabalpur line would strengthen transmission capacity from power generating plants in Chhattisgarh and Odisha to key load centres in western and northern region.
Due to over generation and lack of synchronised transmission, these regions suffer from power-supply congestion.
“Besides eliminating bottlenecks in connecting power producers and distribution entities, the project would ensure stability and reliability of the grid,” said Pravin Agarwal, chairman, Sterlite Grid.
By commissioning all the elements of the Jabalpur project, Sterlite Grid has become the first private developer to complete 765 kV double-circuit transmission system, the firm said.
The company has three more projects in the pipeline.
More From This Section
Don't miss the most important news and views of the day. Get them on our Telegram channel
First Published: Sep 19 2015 | 12:46 AM IST