Delay in Induction of Scorpene Submarine

Image

Delhi
The original schedule of delivery of the first submarine was December, 2012 which has since been revised.

The difficulties faced by M/s. MDL during the course of procurement of materials from foreign vendors had mainly led to the delay.

The builder shipyard has a contract with M/s DCNS, France for construction of Scorpene Submarines. M/s DCNS deputes its personnel / consultant to guide the construction of the submarines as per the collaboration agreement.

The shipyard has undertaken augmentation of the manpower, infrastructure and industrial means in a phased manner to meet the production targets. Production capabilities have also been augmented.

This information was given by Defence Minister Shri Manohar Parrikar in a written reply to Dr. Chandan Mitra in Rajya Sabha today.