Moreover, the progress depends on the date of the selection of the Smart City. After selection, it takes around 18 months in setting up Special Purpose Vehicle (SPV), procuring Project Management Consultant (PMC) firm, hiring Human Resources, preparing Detailed Project Reports (DPRs) and then call for tenders. For Cities selected in Round 1 (January 2016), where 18 months have lapsed, about 51% of the projects have either been tendered or are under implementation. In Round 2 & 3, nearly all the cities have set up SPVs.
Since the launch of the Smart Cities Mission Rs. 9,939 crores hasbeen released by Government of India to Smart Cities. Against this, 753 projects worth Rs. 24,511 crores have been completed or started work on-ground.Further, about 287 projects worth Rs. 14,296 crores are in tendering stage and the works on-ground is expected to start very soon.This is one of the fastest progress demonstrated in the urban sector considering the scale and novelty of the Mission.
Status of the implementation of the Projects under the Smart Cities Mission
Status Number of projects Cost (INR crore)Work Completed 243 4,583Work Order Issued 510 19,928Tender issued 287 14,296DPR Approved 60 3,659DPR under preparation 1,908 96,518In addition, the Smart Cities are also generating funds by mobilizing internal revenue sources, public-private partnerships, value capture financing, convergence, etc. These additional funds are also helping the cities to meet the requirement for project financing.
Powered by Capital Market - Live News
Disclaimer: No Business Standard Journalist was involved in creation of this content