Delay in permissions can't be termed force majeure

The National Commission found that delay was caused due to submission of plans which were not in consonance with the statutory rules and regulations

Image
premium

Jehangir B Gai
B Rudragouda and seven other family members had individually booked apartments in Godrej Platinum, a housing project by Godrej Buildwell at Hebbal Village, Kasaba Hubli, North Bengaluru.

The agreement between Rudragouda and Godrej executed in October 2013 was for the purchase of a four-bedroom apartment measuring 3,905 sq ft, along with two parking slots, for a consideration of Rs 1,79,82,000. Delivery was to be given in September 2015, with provision for a grace period of six months. The agreement provided that the builder would pay compensation for any delay by paying 12 per cent interest.

Even after the expiry of the grace