Punjab Vigilance Bureau sleuths along with road construction engineers today conducted a surprise check of Mohali's airport road and found that prescribed material had allegedly not used in its construction.
On the basis of complaints regarding non-worthiness of the recently constructed road, the Vigilance Bureau's Chief Director B K Uppal along with senior PWD and GMADA engineers and Central Road Research Institute (CRRI) experts inspected it, a spokesman said.
They excavated the road at two points and prima facie it has been found that the 200-feet thoroughfare was not designed properly and sub-standard material was used, he said.
Also Read
Uppal said that the GMADA had already received a sampling report from the CRRI.
Experts from the CRRI have been asked to collect some more samples from the locations selected by the technical teams of vigilance bureau, PWD (B&R) and GMADA, and submit a report, the bureau's chief director said,
Uppal said that on the basis of CRRI reports further action would be initiated against the guilty engineers and the contractor.
Disclaimer: No Business Standard Journalist was involved in creation of this content
More From This Section
Don't miss the most important news and views of the day. Get them on our Telegram channel
First Published: Sep 19 2017 | 8:57 PM IST