Thanjavur-Tiruchi electrification work begins

Electrification work on the Thanjavur-Tiruchirappalli section has commenced and is expected to be over by this year-end, a railway official said Wednesday.
The project began in April but was delayed to facilitate the track-doubling work.
The work is being carried out by the Central Organisation for Railway Electrification (CORE).
A senior official of the organisation said the overhead wiring work was on from Golden Rock to Solagampatti. The project in the Tiruchi-Thanjavur section was part of the Tiruchi-Karaikal electrification work, he said.
Electrification work was on in portions of the Thanjavur and Tiruvarur track and from Tiruvarur to Karaikal, he said, adding that a power sub-station would established as part of the project at Tiruvarur.
Overhead electrification of the stretch from Thanjavur to Karaikal was expected to be completed by June, the official added.
Disclaimer: No Business Standard Journalist was involved in creation of this content
More From This Section
Don't miss the most important news and views of the day. Get them on our Telegram channel
First Published: Oct 17 2018 | 6:00 PM IST