Ferro chrome producer Indian Metals & Ferro Alloys Ltd (IMFA), announced the commissioning of the first unit of its 2x60 MW captive power plant located at Choudwar, Odisha.

While the interim captive power generation capacity stands at 198 MW with synchronization of the first unit, it shall go up to 258 MW when the second unit is commissioned in February 2013.

Set up at a cost of more than Rs 600 crores, the 120 MW CPP will primarily cater to IMFA’s captive requirement of electricity for its ferro chrome production. However, in the short term there is going to be a surplus of about 50 MW which can be supplied to the grid although plans are already underway to increase smelting capacity to absorb the entire generation.

Power injected by the Company at Choudwar will help system parameters in the surrounding areas including Bhubaneswar and Cuttack. The Company is going to lay the second circuit from Choudwar to Salepur which will be a part of the OPTCL system as well as state of the art ‘High Tension Low Slag’ (HTLS) conductors between its complex and the Choudwar Grid. This will help in evacuating more than 100 MW besides providing stable power to Salepur and Kendrapada.

The boiler and pollution control equipment have been procured from Thermax which is also the EPC contractor while the Turbine has been procured from HTC, China and Generator from Jinan Power Equipment Factory, China.

“Combined with the imminent start of the captive coal block, the foundation is in place for a boost to the topline and bottomline going ahead,” said Subhrakant Panda, Managing Director of the company.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Jan 08 2013 | 1:27 PM IST

Next Story