MCL refuses to commit additional coal supply to NTPC

Image
Sadananda Mohapatra Kolkata/ Bhubaneswar
Last Updated : Jan 24 2013 | 2:10 AM IST

National Thermal Power Corporation (NTPC), which had sought the state government intervention to direct Mahanadi Coalfields Ltd (MCL) for additional coal supply by rail to its Talcher power station, received a major jolt as the Coal India subsidiary has declined to give any commitment.

“It is requested that the officials of TTPS (Talcher Thermal Power Station) may be advised to make arrangement for lifting coal through belt mode and will be supplemented through rail mode to the extent possible,” said A K Tiwari, director (production) of MCL to the state energy department.

Between April and October, coal supplies to TTPS were 15.91 lakh tonne against pro-rata Fuel Supply Agreement (FSA) quantity of 13.88 lakh tonne. Since the power producer has already received excess coal, no guarantee can be given on additional coal supply, the miner justified.

MCL has suggested that having its factory near the coal mines, the NTPC plant must make efforts to get maximum coal through belt system and not via rail which is both time consuming and uncertain.

The Talcher plant of NTPC has an installed capacity of 460 Mw, which consisted of two 110 Mw units and four units each with a capacity of 60 MW. The entire power generated at this plant is dedicated for supply within Odisha.

The plant requires 9,500 tonne coal everyday and also needs to build up stock of about 250,000 tonne coal for summer and rainy season, when coal output drops.

“We currently have about 40,000 tonne stocks with us, which will only last for just five days. If there is any supply disruption between December and March for any reason, we will have no option but to curb output,” said Himachal Panda, general manager of TTPS.

“The situation will be worse in the summer and rainy season if we do not get two coal rakes per day from MCL apart from belt supplies,” he added.

The power generator had sought the government intervention as coal supplies by rail was 13 rakes in August and just six rakes in September, against NTPC’s demand of 45 to 60 rakes per month. Even though the supply situation improved in November to 30 rakes, the TTPS official said in absence of commitment from MCL, it would be difficult to guarantee desired power generation for the state.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Dec 06 2012 | 12:06 AM IST

Next Story