350 infra projects show cost overrun of Rs 2.65 lakh cr: Govt

Major steps have been undertaken to ensure completion of Central Sector Infrastructure Projects without time and cost overruns

EPFO, pension, retirement
Photo: Shutterstock
Press Trust of India New Delhi
Last Updated : Dec 20 2017 | 4:49 PM IST
As many as 350 infrastructure projects, each worth Rs 150 crore or above, have shown cost overrun of Rs 2.65 lakh crore due to various reasons including delays, Parliament was informed today.

"As on October 1, 2017, a total of 1,263 projects were on the monitor of this Ministry. Of these, 297 are showing time overruns, 350 are showing cost overruns and 103 are showing both time and cost overruns. These 350 projects are showing cost overrun of Rs 2.65 lakh crore," Statistics and Programme Implementation Minister Vijay Goel said in a written reply to the Lok Sabha.

The Ministry of Statistics and Programme Implementation monitors on-going Central Sector Infrastructure Projects costing Rs 150 crore and above on time and cost overruns on the basis of information provided by the project implementation agencies.

The minister informed the House that causes for time overruns are project-specific and depend on a variety of technical, financial and administrative factors.

He added that as reported by the project implementing agencies, the main reasons for the delays pertain to land acquisition, environment and forest clearances, funding constraints, rehabilitation and resettlement issues, local body/municipal permissions, utility shifting and contractual issues.

The minister also said that the range of delay in the 297 projects is from 1-261 months.

Major steps have been undertaken to ensure completion of Central Sector Infrastructure Projects without time and cost overruns.

The steps include rigorous project appraisal, On-line Computerised Monitoring System (OCMS), setting up of Revised Cost Committees in the ministries for fixation of responsibility, regular review of infrastructure projects by administrative ministries concerned, and setting up of Central Sector Projects Coordination Committees (CSPCCs) in the states under the Chief Secretaries for removal of bottlenecks.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Dec 20 2017 | 3:00 PM IST

Next Story