Demand notice must be served properly to buyer

The purchaser couldn't be termed a defaulter since the demand letter had not been served properly, and especially when he paid the amount on receiving a reminder

Image
Jehangir B Gai
3 min read Last Updated : Aug 01 2021 | 8:10 PM IST
Utpal Trehan booked a 3-BHK flat in Gurgaon costing Rs 45,12,000 in New Heights, a project by DLF Home Developers. The agreement executed on December 3, 2008, stipulated that possession would be given within 36 months. If there was a delay, a monthly compensation of Rs 5 per square feet (sq. ft.) would be paid.

On March 26, 2009, the builder informed that project commencement had got delayed as final environment clearance had not been received. The payment schedule was converted to construction-linked plan. The amount paid till then would be treated as advance payment carrying interest at 13 per cent per annum, and would be adjusted against the subsequent instalment. Compensation for delayed possession was increased to Rs 10 per sq. ft. per month.

Trehan paid the instalments on time. However, he did not pay the demand of Rs 1,66,050 towards External Development and Infrastructure Development Charges, disputing it as being illegal and unjustified. He did not pay the subsequent instalment demanded on December 29, 2011, on time as he did not receive the demand letter. However, he paid it on receiving a reminder.

While offering possession, the builder sent a statement of account showing an outstanding balance of Rs 9,00,382, which included Rs 1,226 towards interest for delayed payment, and Rs 1,53,900 for increase in area. Rebate for timely payments and compensation for delayed possession were not given. The builder also started demanding maintenance charges.

Trehan filed a complaint before the Delhi State Commission. The builder contested, pointing out that the instalment demanded on December 29, 2011, was sent by courier and someone named Gita had received it, so the demand for delayed payment was justified.

While the complaint was pending, the builder resolved some of the billing issues. The remaining disputes were adjudicated by the State Commission. Its order was challenged by both the parties.

The National Commission observed that the dispute was now limited to rebate for timely payment and compensation for delayed possession. It noted that it was the builder's duty to ensure that the demand notice was served to Trehan or an adult family member. There was nothing on record to show that Gita, who had purportedly accepted the notice, was a family member or was authorised to accept it. So, the purchaser could not be termed a defaulter on the basis of a demand letter that had not been properly served, especially when the amount was promptly paid on receipt of the reminder. The National Commission confirmed that Trehan would be entitled to rebate for timely payment.

Regarding compensation for delayed possession, the Commission observed that the builder had already given certain benefits and paid compensation, and Trehan had accepted them. So, it held that no further compensation could be claimed.

Since the agreement provided that maintenance charges would be payable from the date of receipt of the Occupation Certificate, the Commission held the builder's demand to be valid and justified.

Accordingly, by its order of July 23, 2021, delivered by the Bench of C. Viswanath and Ram Surat Ram Maurya, the National Commission modified the order and awarded costs of Rs 50,000 to Trehan.

The writer is a consumer activist

One subscription. Two world-class reads.

Already subscribed? Log in

Subscribe to read the full story →
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

Disclaimer: These are personal views of the writer. They do not necessarily reflect the opinion of www.business-standard.com or the Business Standard newspaper

Topics :Real Estate CONSUMER PROTECTIONinfrastructure

Next Story