Fix liability for loss in electrification contracts: Parl panel to Railways

The matter pertained to the execution of Overhead Equipment (OHE) work in the SCR zone, for which two contracts were awarded worth Rs 35.36 crore in 2017-18

Indian Railway
It has also favoured bringing in a provision for the recovery of financial loss to the exchequer along with penal interest consequent to the fixing of responsibility. | Representative Photo: Shutterstock
Press Trust of India New Delhi
3 min read Last Updated : Mar 31 2025 | 10:30 PM IST

A parliamentary committee has directed the Railway Ministry to fix responsibility of officers for a financial loss of Rs 9 crore in electrification work contracts in the South East Central Railway Zone in 2017-18.

It has also favoured bringing in a provision for the recovery of financial loss to the exchequer along with penal interest consequent to the fixing of responsibility.

The matter pertained to the execution of Overhead Equipment (OHE) work in the SCR zone, for which two contracts were awarded worth Rs 35.36 crore in 2017-18.

However, the audit report found that the prerequisite civil works were not ready before awarding the contract because of a lack of coordination between the civil and electrical departments of the SECR, leading to inefficiencies and financial losses.

It noticed that the contractors supplied materials worth Rs 9.0 crore during the contract period (2017-18) but could not execute works due to the non-availability of a clear worksite.

"This led to the short closure of contracts without any progress in the execution portion. Supplied materials worth Rs 9.0 crore could not be fully utilised for the intended purpose," the Committee on Public Accounts said in its report submitted to the parliament recently.

The Railway Ministry, in its action taken reply, said that it would ensure strict adherence to a comprehensive compliance checklist for the tendering process.

Dissatisfied with the Ministry's response, the Committee expressed regret and said, "At this stage, the Committee can only recommend that an inquiry be conducted to fix responsibility for such lapse. Resultantly, material worth Rs.9.0 crore could not be fully utilised for want of a clear site."  "In the opinion of the Committee, the Ministry has not befittingly responded to the pinpointed recommendations of the Committee nor has undertaken any analysis of the factors which hindered or delayed the completion of the civil work," the report said.

The report also highlighted the Committee's concern regarding the Ministry's lack of efforts to mitigate the financial losses that occurred owing to a lack of coordination and resource management practices, despite concerns raised by the Audit.

"In order to ensure timely execution, the Committee urge that there ought to be a provision for recovery of financial loss to the exchequer along with penal interest consequent to the fixing of responsibility," the report said.

It added, "The Committee are unhappy to note the perfunctory manner and callous disregard with which the Ministry have furnished action taken replies on such an important observation/recommendations of the Committee, which was meant to streamline procurement process and award of contract in a time bound manner."  Asking the Ministry to pay adequate attention to operation and maintenance in the procurement process so that slip-back instances could be minimised, the Committee urged that in order to avoid instances of delay and cost overruns, it needs periodical evaluation of monitoring and reporting mechanisms insofar as management of funds is concerned.

(Only the headline and picture of this report may have been reworked by the Business Standard staff; the rest of the content is auto-generated from a syndicated feed.)

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

Topics :Indian RailwaysElectrificationRailway BoardBudget session

First Published: Mar 31 2025 | 10:30 PM IST

Next Story