MCL Kaniha project oustees unwilling to cede land

Image
BS Reporter Kolkata/ Angul
Last Updated : Jan 19 2013 | 11:47 PM IST

Mahanadi Coalfields Limited’s (MCL) plan to kick off the 10 million tonne per annum Kaniha open cast coal mining project at Talcher Coalfields has suffered further delay. The villagers to be displaced by the project are reluctant to cede their land for the project unless their demand for 41 jobs under the ‘C’ category is fulfilled by the company.

The project has already suffered delay for about two years even though two other projects named Kulda and Bhubaneswari which were envisaged at the same time have started production a year ago. The tenants belonging to Jarada of Kaniha area do not allow the MCL authorities to start mining on their land unless these cases related to the 41 jobs under the ‘C’ category are cleared by the company.

”So far 441 job cases out of the total of 482 jobs which were demanded have been cleared by the company in consultation with the Angul district authorities as per the eligibility in that village”, said an MCL official associated with the project.

The company authorities are helpless in providing jobs to the remaining oustees as they belong to ‘C’ category under the 1989 rehabilitation policy of the Orissa government. A person losing total homestead land but not losing total agricultural land is placed in the ‘C’ category. MCL has stopped giving jobs to the oustees in the ‘C’ category from 2005 following orders from the government, said the official.

MCL authorities said that they are ready to provide 41 jobs to the ‘C’ category of land oustees if they have lost all their all homestead land at Jarada, but the relaxation should be a one time affair and should not be an antecedent for others to follow. MCL is in favour of arbitration by any government body to settle these cases as a one time relaxation for the ‘C’ category oustees.

The Rehabilitation and Peripheral Development Advisory Committee (RPDAC) which should have taken the decision on this issue has not failed to convene any meeting since November last year.

In 2008-09, the MCL authorities had fixed a production target of one million tonne from the Kaniha project.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: May 28 2009 | 12:12 AM IST

Next Story