SC dismisses L&T appeal on NTPC tender

Image
Press Trust of India New Delhi
Last Updated : Jan 20 2013 | 1:24 AM IST

The Supreme Court today dismissed Larsen & Toubro's appeal challenging its disqualification from participation in state-run NTPC's Rs 15,000 crore power equipment tender and seeking a stay on the bidding process.

A bench comprising Justice Altamas Kabir and Justice Cyriac Joseph declined to stay an interim order by the Delhi High Court rejecting L&T's plea for suspending the bidding process for the tender after its bid was disqualified on technical grounds.

However, the apex court directed the High Court, where the matter is still pending, to decide the issue expeditiously.

"This SLP (special leave petition) against interim order dated 14/9/2010, where the petitioner's interim prayer was rejected... Since writ petition is still pending before the High Court, we do not wish to express any views. We are also not inclined to entertain this SLP and is dismissed," the bench said.

"However, since the matter is pending before the High Court and it has a huge financial stake, the High Court is requested to decide on this writ petition as early as possible," the bench said, directing the High Court not to give any adjournment on November 11, the next date of hearing.

In a setback for L&T, the Delhi High Court had on September 14 refused its plea to stay the bidding process for NTPC's tender, after the infrastructure major was disqualified from participation, ostensibly because it did not match the technical criteria for selection.

The High Court had also refused to intervene in the bidding process.

L&T had dragged NTPC to court after its bid for the Rs 15,000 crore bulk tender was disqualified by the power company, citing technical irregularities. However, following the rejection of its plea for a stay on the bidding process, it had approached the apex court.

NTPC had issued a tender for bulk ordering of supercritical power equipment with a cumulative generation capacity of 7,200 MW, with the caveat that the bidder should have a manufacturing facility in India in order to promote domestic companies.

L&T Power was disqualified by NTPC from supplying boilers and turbines under the tender on the ground that the technology collaboration agreement for the equipment to be supplied was between its parent (L&T) and Mitsubishi Industries Ltd and not directly with L&T Power.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Oct 25 2010 | 5:29 PM IST

Next Story