Clearing roadblocks: Ministry's final push to rescue 14 highway projects

The ministry said some of the highway projects were delayed over the issue of road over-bridges and road under-bridges with the Indian Railways

Highway projects, national highway project
Megha Manchanda New Delhi
Last Updated : Aug 08 2018 | 5:31 AM IST
The Ministry of Road Transport and Highways, in a last-ditch attempt, has come up with another mechanism for saving the 14 remaining projects, though with riders.

The ministry may adopt a risk-and-cost approach or model by which the National Highways Authority of India (NHAI) will take over the highway projects where 60-70 per cent of construction work is complete.

It would then construct the project and recover some cost from the annuity and, being the road developer, the government would have the first right on annuity, an official in the know said. The concessionaire will also pay a 20 per cent fine on the remaining (30-40 per cent) work to the NHAI.

“We would not like to call it a model (risk and cost), rather it is a drive to revive the remaining projects that are stuck due to some issue or the other,” a senior road ministry official told Business Standard.

He said the 14 languishing projects would be dealt with on a case-by-case basis because they are delayed owing to various reasons. These projects belong to Transtroy (India) Ltd (4), Madhucon Projects (3), IL&FS (1), Era Infra Engineering (3) and VIL Ltd (3).

Era Infra Engineering is under the Corporate Insolvency Resolution Process. Queries sent to the remaining companies did not elicit a response.


Some experts say there should be punitive action against these companies. One industry expert said they should be blacklisted for two-three years or some other kind of punishment should be there.

In 2014, 163 of 982 National Highway projects across the country were delayed because of various reasons.

Road Transport Minister Nitin Gadkari had said the main reasons for delay were land acquisition and shifting of utilities, contractual issues, arbitration, and environment and forest clearances.

The ministry said some of the highway projects were delayed over the issue of road over-bridges (ROBs) and road under-bridges (RUBs) with the Indian Railways. This was later sorted out by an agreement between the two ministries to build more ROBs and RUBs.

To expedite work on delayed projects the central government addressed the major bottlenecks by bringing in the exit policy for equity investors and concessionaires, rescheduling premiums for stressed projects, mutual termination and cancellation of awarded road projects and subsequent re-bidding, revamping the dispute resolution mechanism etc. 


“Earlier the banks were a bit queasy in funding the languishing projects but the government itself pushing for completing these projects is a better idea. Roads are a public utility and should be addressed on priority,” former road secretary Vijay Chhibber said.

Last year, Union Transport Minister Nitin Gadkari had said the government would not shy away from terminating around 10 highway contracts that had turned “chronic” over land acquisition and environment clearance delays. They would then be put up for re-bidding.

The factors responsible were delays in clearances, lack of supporting infrastructure, law and order problems, delay in shifting of utilities, pre-project activities, equipment supply, fund constraints and geological surprises. In 2016-17, the central government began the exercise of re-bidding some stalled projects flagged by banks as likely non-performing assets.

Some contracts were re-tendered by the government and the NHAI and global investors such as Macquarie, Brookfield and Cube Highways picked up stakes in 10 highway projects worth Rs41.50 billion. 

The Cabinet in May 2015 approved a policy that allowed project concessionaires to divest 100 per cent equity two years after completion of construction.

Clearing roadblocks

Macquarie, Brookfield & Cube Highways picked up equity in 10 national highway projects 
 
Private promoters had exited these projects 
 
Cabinet approved exit policy for developers in May 2015 
 
Exit policy allows developers to divest 100 per cent equity in projects two years after the completion of construction

One subscription. Two world-class reads.

Already subscribed? Log in

Subscribe to read the full story →
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

Next Story