EPC road firms could face slowdown in revenue growth in FY20, FY21: Crisil

Slower project awarding and delayed receipt of 'appointment date' (on which projects are kicked off) from the NHAI are the main contributors to this decline

Increasing hurdles: Arbitration claims against NHAI on the rise
Megha Manchanda New Delhi
3 min read Last Updated : Nov 06 2019 | 9:39 PM IST
Revenue growth of road developers in the engineering, procurement, and construction (EPC) segment could halve in 2019-20 (FY20) and 2020-21 (FY21) to 15 per cent, compared to 30 per cent in 2018-19 (FY19), according to a CRISIL study.

Slower project awarding and delayed receipt of “appointment date” (on which projects are kicked off) from the National Highways Authority of India (NHAI) are the main contributors to this decline.

“The NHAI awarded 7,400 km in FY18, which slowed the following year to about 2,200 km. In the current financial year (FY20) and the next (FY21), this is expected to be 4,000 km a year,” said Sachin Gupta, senior director, CRISIL Ratings. 

He added, “Delay in declaring appointed dates for the projects awarded is primarily due to issues in land acquisition. CRISIL’s analysis of 119 hybrid annuity model (HAM) projects shows almost 30 per cent of these have not received appointed dates more than a year after these were awarded.”

CRISIL, in its study of 75 companies, said this would not affect the credit profiles of the EPC companies. There are several reasons for this.

First, in FY19, these companies had a healthy order book of Rs 2 trillion. This is thrice their revenue and provides a high revenue expectation for the next two years. 

Then, these firms have kept a check on their debt levels while pursuing growth. At the consolidated level, the capital structure was robust as on March 31 this year.

The improvement was largely because of focus on awarding through EPC and HAM routes, which entail lower equity requirement. Additionally, renewed interest from global funds gave a fillip to the sector, and divestment of special purpose vehicles through infrastructure investment trusts or asset-level sale supported the improvement in capital structure.

Third, while a delay in receipt of appointed date may lead to a delay in recognising revenue for some of the projects, there is an assurance that a project, once started, will not be stalled. 

This is because the NHAI notifies the appointed date only when most of the land (80 per cent for HAM projects) has been procured. 

Thus, once a project is under construction, there is limited risk of delays because of non-availability of land and thereby minimal impact on credit profile of the EPC companies.

There is a risk that any further delay in declaring appointed dates could result in termination of some of the awarded projects.

“The concession agreement for HAM allows for mutual termination of a project in case the appointed date is not received within a year of signing of this agreement, and a few projects have indeed been terminated on this ground recently. An increase in project terminations would further impact the revenue growth of these companies,” Sushmita Majumdar, director, CRISIL Ratings.

One subscription. Two world-class reads.

Already subscribed? Log in

Subscribe to read the full story →
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

Topics :CrisilEPC companiesroadwaysEPC projectsCrisil report

Next Story