Kudankulam second n-power unit to undergo systems check

Image
IANS Chennai
Last Updated : Feb 28 2014 | 3:05 PM IST

The Nuclear Power Corporation of India (NPCIL) is hoping to carry out a full systems check, technically called hydro test, of its second 1,000 MW atomic power reactor at Kudankulam Nuclear Power Project (KNPP), said a senior official.

The company is also hoping to approach the Atomic Energy Regulatory Board (AERB), the sectoral regulator to increase the power levels of its first unit at KNPP.

"We are planning to do test in a week's time. This is a preparatory step for the reactor's hot run," R.S. Sundar, KNPP site director, told IANS.

Hot run is a trial run of the reactor with dummy fuel assemblies. The dummy fuel assemblies, made of lead instead of uranium are the exact replica of the actual nuclear fuel assemblies, both in dimension and weight.

The unit has achieved a physical progress of 96.74 percent as in January.

When asked about the functioning of the first unit, Sundar said it is running at 73 percent power levels and various tests are being carried out.

"We hope to complete all the tests in one week's time and approach AERB with an application to increase the reactor power levels beyond 75 percent," Sundar said.

India's atomic power plant operator NPCIL is setting up two 1,000 MW Russian reactors at Kudankulam in Tirunelveli district, 650 km from here. The total outlay for the project is over Rs.17,000 crore.

KNPP is India's first pressurised water reactor belonging to the light water reactor category.

The first unit attained criticality July 2013, which is the beginning of the fission process.

In August 2013, the AERB gave its permission to generate power up to 50 percent (500 MW) of the rated capacity.

Last month AERB allowed the unit to generate power up to 75 percent capacity.

According to Sundar, it normally takes around nine months for a similar reactor to be commercially operational from the time it begins the nuclear fission process for the first time.

The NPCIL is hoping to operate the first unit on a commercial basis this April.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Feb 28 2014 | 3:02 PM IST

Next Story