Delay in construction is builder's problem

National Commission observed that Unitech had failed to produce any evidence to substantiate its defence

Real estate
Jehangir B Gai
Last Updated : Jun 28 2018 | 6:58 AM IST
Unitech was allotted land by the Greater Noida Industrial Development Authority for developing a Group Housing Complex — Unitech Horizon. Since the booking phase was over, Sameer Dewan was put in touch with brokers to get the booking transferred from allottees who were no longer interested.

One broker introduced Dewan to Ranjiv and Geetika Jaggi who wanted to sell their allotment rights to flat number 403 in Tower 22. On inquiring with Unitech, Dewan was informed that the construction was going on at a rapid pace and the flat should be available by November 15, 2008, as scheduled. After builder's assurance, Dewan purchased the allotment rights from Jaggis and asked Unitech to transfer the booking in his favour. The builder agreed. The price was fixed at Rs 4,782,207.

Dewan paid Rs 4,572,761 in instalments. The balance was payable on possession. But the builder failed to give the delivery. Dewan filed a complaint before the National Commission for a refund along with 18 per cent interest and litigation costs. Unitech contested, contending that the farmers whose lands had been acquired by the Noida Development Authority had gone on agitation for a hike in compensation, which hampered construction. Also, the National Green Tribunal had restrained Unitech from extracting ground water for construction. The delivery was delayed due to reasons beyond its control.

The Commission observed that Unitech had failed to produce any evidence to substantiate its defence. Besides, the flat was not ready even now, despite more than seven years have elapsed since the promised date of possession.

The builder tried to argue that the agreed date of possession was November 15, 2008, while the complaint was filed in 2016, so it would be barred by limitation and ought to be dismissed. Rejecting the argument, the National Commission observed that possession had neither been offered nor refused. So, there is a recurrent cause of action when a complaint pertains to non-delivery of possession. The Commission concluded that the complaint was in time.


On compensation, the builder tried to argue that its maximum liability for delay in delivery would be governed by the terms stipulated in the agreement for sale, which provide for a compensation of Rs 5 per sq ft a month.

The Commission rejected the contention. It observed that the clause would be applicable only when the delay is for a reasonable period due to unavoidable circumstances, which need to be substantiated. The builder cannot shield himself behind such a clause. It also observed that if such contention is accepted, it would wrongly encourage developers to use buyers’ money paid at a nominal cost instead of borrowing funds at the market rate.

Accordingly, by its order of June 6, 2018, delivered by Justice Ajit Bharihoke, the National Commission ordered Unitech to refund the entire amount of Rs 4,572,761 along with 10 per cent interest computed from the date of payment of each instalment. Additionally, Rs 10,000 was awarded as litigation costs.

(The author is a consumer activist)

One subscription. Two world-class reads.

Already subscribed? Log in

Subscribe to read the full story →
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

Next Story