CAG finds fault with Railways' PPP projects execution

Image
Press Trust of India New Delhi
Last Updated : Jul 18 2014 | 4:17 PM IST
Finding fault with railways' PPP projects execution, the Comptroller and Auditor General (CAG) has observed that the national transporter failed to adhere to standard procedures and rules were violated in selection of private players.
The CAG in its latest report tabled in Parliament today has found that faulty assessment was made on internal rate of return (IRR), project approvals were marred by delays and there was lack of any monitoring mechanism for these projects.
The audit body found that railways did not formulate any model agreement for execution of the projects within the stipulated time frame, nor did it adopt the model prescribed by the Planning Commission for PPP projects in infrastructure sector.
Taking the example of Viramgam Mahesana Private Ltd (VMPL), a gauge conversion project between Viramgam and Mahesana to cater to the defence requirement, the CAG said the approval of Finance Ministry was not taken for build operate and transfer (BOT) mode of payment of access charge.
"The annual earning of the project was Rs 6.45 crore against the annual access charge payment of Rs 15.94 cr. The project sustained loss despite estimated internal rate of return (IRR) of 22 per cent," the audit report said.
The CAG criticised the lack of a model concession agreement (MCA), a framework of contract that sets the terms for incentives and targets for the private player.
Railways did not formulate model concession agreement for ppp projects.
"The audit observed that Railway Ministry did not formulate any MCA for these projects. On the contrary, it finalised each agreement separately based on its experience in Pipavav Rail Corporation Limited (PRCL), the first PPP project and the same was adopted as a benchmark while finalising subsequent agreements," the report said.
It noted that though monthly progress reports were being prepared by special purpose vehicle (SPVs), there were however, no records confirming the fact that the progress of the projects was being monitored by the construction progress review board.
"The role of Railway Ministry for monitoring the performance of projects was not laid down in any of the concession agreements," it said.
The CAG has also observed that absence of model concession agreement led to adoption of varying approaches towards fixation of concession period, lease rent and liability of railways at the time of transfer of assets by the SPVs.
Railways launched schemes to supplement investment in partnership with private players for specific projects to develop port linkages. PPP is one of such initiatives to develop infrastructure in railways.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Jul 18 2014 | 4:17 PM IST

Next Story