NHPC suffered expected loss of Rs 233.56 cr due to flash floods in Sikkim

Insurance amount claimed and realised by the listed entity for the loss/ damage is "Nil" (as on date), it informed

NHPC-hydro power producer
It is anticipated that there will be a time delay of at least six months and consequent cost-overrun of the project
Press Trust of India New Delhi
2 min read Last Updated : Oct 18 2023 | 3:55 PM IST

State-run hydro power giant NHPC on Wednesday said it suffered an expected loss of Rs 233.56 crore due to flash floods in its Teesta-VI hydro power project in Sikkim.

The project was affected due to flash floods in Teesta basin on October 4, 2023.

"Teesta-VI Hydro Electric Project, Sikkim (500 MW) being executed by Lanco Teesta Hydro Power Ltd, a wholly-owned subsidiary of NHPC Ltd, which was affected due to flash flood in Teesta Basin on October 4, 2023," the company said in a regulatory filing.

The expected quantum of loss/ damage caused due to the natural calamity/ other force majeure events is Rs 233.56 crore approximately, it said.

The company further said that all assets/ works of Teesta-VI HE project are insured under the Construction All Risk (CAR) Policy, subject to excess clause and loss limit.

Insurance amount claimed and realised by the listed entity for the loss/ damage is "Nil" (as on date), it informed.

However, it said that the formal claim shall be lodged and amount for damage/ loss would be realised in due course of time, as per the CAR policy.

Talking about the details of steps taken to restore normalcy and the impact of the natural calamity/ other force majeure events on production or service, financials of the entity, it said an assessment is being done and restoration works are under progress.

It is anticipated that there will be a time delay of at least six months and consequent cost-overrun of the project.

(Only the headline and picture of this report may have been reworked by the Business Standard staff; the rest of the content is auto-generated from a syndicated feed.)

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

Topics :NHPC solar projectNHPCSikkimNortheast floods

First Published: Oct 18 2023 | 3:55 PM IST

Next Story