Compensation for grid curtailment to benefit renewable sector: Ind-Ra

Proposed compensation at PPA tariff to restrict fall of annual debt service coverage ratio to 0.06%

Power, energy, India
CHARGING UP The game changer would be a push for electric mobility. If a switch can be made to moving people and goods with only electricity, India would become an almost fossil-fuel-free economy
Press Trust of India Mumbai
Last Updated : May 23 2017 | 5:18 PM IST
The Centre's proposed compensation mechanism for existing renewable energy projects will protect the cash flows to an extent from grid curtailments and will also ensure a favourable operational environment for renewables sector, said India Ratings.

"If the proposal is adopted it will protect the cash flows to an extent from grid curtailments and also ensure a favourable operational environment for renewable energy projects. It will also be positive for wind and solar energy developers," the ratings agency said in a statement in Mumbai.

Historically, power purchase agreements (PPAs) signed for renewable energy projects have failed to address the grid issues and lacked a mechanism to compensate for energy loss.

According to Ind-Ra, the annual debt service coverage ratio (DSCR) slips by 0.12 times for 10 per cent of energy curtailment and the 50 per cent proposed compensation at PPA tariff will restrict the fall by half at 0.06 per cent.

The developers have bridged any cash flow shortfall in debt service through a combination of or individually tapping debt service reserve or drawing working capital limits or sponsor support, it said.

"The recent reverse auction of 750MW solar capacity in Rewa solar bid included the provisions for compensation for deemed generation in case of curtailment. The recommended PPA format for future wind and solar projects should also include provisions for curtailment compensation."

It, however, maintained that the absence of clarity on two possible reasons for grid curtailment - low system demand and grid security - could however pose new challenges for developers.

"Further clarity by the authority/utilities to define the terms and spell out when these measures will need to be opted for could allay possible apprehensions of the developers and make the process more transparent," the agency said.

Also, in the proposed framework it is unclear which situations will be identified as low system demand incidences, since the network operators have the option to shut down a thermal plant which is falling below its technical minimum operating level, it said.

Citing the recent forced shutdown of some thermal power plants by Tamil Nadu discom during high wind season to enable full evacuation of wind power generation, Ind-Ra said there is a possibility of utilities taking refuge under the low system demand and curtail high costs renewables to save costs leading to reduced cash flows.

"We believe that utilities should project demand for the next six months to one year along with definition of low system demand. This transparent process could allay the fears of developers when actually the demand plummets," it said.

The compensation will also incentivise grid operators and distribution utilities to reduce curtailments and benefit renewable energy developers in scheduling and forecasting and enable integration of increasing renewable energy capacity.

In FY17, grid curtailment was prevalent for wind projects in Rajasthan (up to even 45 per cent energy curtailed compared to 90 per cent of plant load factor) and solar projects in Tamil Nadu.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: May 23 2017 | 5:17 PM IST

Next Story