Lower Subansiri project incurring daily loss of Rs 10 crore

Anti-dam activists of Assam raised safety-related issues, which brought work to a halt in December 2011

Image
Press Trust of India Itanagar
Last Updated : Jun 23 2014 | 10:46 AM IST
The Lower Subansiri hydro- electric project at Gerukamukh on the Assam-Arunachal border is incurring a daily loss of Rs 10 crore after anti-dam activists of Assam raised safety-related issues.

The 2000-MW project in the Subansiri river, the largest in the country and being executed by the NHPC, has run into rough weather after the work for the project came to a halt in December, 2011.

The height of the dam was initially planned for 257 metres, but later it was reduced to 116 metres after the anti-dam activists under the banner of Krishak Mukti Sangram Samiti in Assam protested.

Also Read

The protesters, led by KMSS president Akhil Gogoi, contend that the dam will have adverse impact on the people living downstream and the flora and fauna.

"We are incurring a loss of Rs three crore per day as the machines and other equipment are lying idle and have already started rusting. The project, which was supposed to be commissioned in March, this year, is incurring a loss of another Rs seven crore per day against revenue generation," Executive Director of the project Rakesh told a group of visiting journalists.

Already more than 55% work of the project has been completed including tunnel, dam, power house and other civil work.

Machines could be seen lying scattered at the project site while most of the workers have been withdrawn from the project site following suspension of work since 2011.

Though the initial estimated cost of the project was Rs 6,285 core (2002-2005), the project authority has already invested Rs 6,600 crore. The cost of the project now has gone up by Rs 1,200 crore.

Beside this, there was a recurring expenditure of Rs 50 crore per month.

"Any more delay will further escalate the cost of the project which will ultimately affect the people in terms of higher cost of electricity as the continuing delay is only adding to the final cost of power," Rakesh pointed out.

He said the apprehension expressed by the anti-dam protesters were ill-founded since it was by no means a mega dam project, but a run-of-the river project with small reservoirs where 10% of the rain water would be stored while the rest would flow downstream.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Jun 23 2014 | 10:31 AM IST

Next Story