The expert committee, headed by Shashi Shekhar, Secretary of Ministry of Water Resources, has informed the green panel that major restoration work has to be carried out to compensate for the damage to Yamuna floodplains.
"It has been estimated that approximately 120 hectares (about 300 acres) of floodplains of west (right bank) of the river Yamuna and about 50 hectares (120 acres) floodplains of the eastern side (left bank) of the river have been adversely impacted ecologically at different magnitudes," it said.
It, however, had imposed Rs 5 crore as interim environment compensation on the foundation for the event's impact on the environment.
Initially, a four-member committee had recommended that AOL Foundation should pay Rs 100-120 crore as restoration cost for "extensive and severe damage" to the floodplains of Yamuna river.
Later, a seven-member expert committee had told NGT that the event organised on Yamuna has "completely destroyed" the riverbed.
"The ground is now totally levelled, compacted and hardened and is totally devoid of water bodies or depressions and almost completely devoid of any vegetation.
"The area where the grand stage was erected (and the area immediately behind it) is heavily consolidated - most likely with a different kind of external material used to level the ground and compress it.
"Huge amount of earth and debris have been dumped to construct the ramps for access from the DND flyover and from the two pontoon bridges across the Barapulla drain," the expert committee had said.
It has said that it will cost Rs 13.29 crore and take almost 10 years to rehabilitate the river floodplain.