L&T terminated contracts of suburban rail project illegally, says K-RIDE

Originally, the scheduled completion time for Corridor-2 (C2) was 27 months, but was extended up to September 30, 2026. The agreement entered upon for Corridor-4 (C4) is valid till October 2026

Larsen & Turbo, L&T
According to K-RIDE, work was delayed because L&T failed to mobilise adequate resources and there was a delay in finalising designs. It also said that the project managers of L&T were frequently changed, affecting the progress of work.
Press Trust of India Bengaluru
2 min read Last Updated : Aug 02 2025 | 10:48 PM IST

The termination of two contracts for Corridor-2 and Corridor-4 of the Bengaluru Suburban Rail Project (BSRP) by Indian multinational conglomerate Larsen & Toubro is a clear violation of agreement conditions, said officials of K-RIDE, a joint venture between the government of Karnataka and the Ministry of Railways, on Saturday.

L&T had terminated the contract on July 31, added K-RIDE.

"L&T has made unreasonable demands of revising contract price within the contract period and converting EPC contract into an itemised Bill of Quantities (BOQ) contract, even though contract condition does not permit the same," stated a press release issued by K-RIDE on Saturday. 

According to the release, L&T had entered into two agreements to perform the work assigned to them in the Corridor-2 (Chikkabanavara to Benniganahalli) and Corridor-4 (Heelalige to Rajankunte) of the suburban railway project, added the release.

Originally, the scheduled completion time for Corridor-2 (C2) was 27 months, but was extended up to September 30, 2026. The agreement entered upon for Corridor-4 (C4) is valid till October 2026.

K-RIDE officials said all reasonable demands of L&T were addressed by them as per the provisions of the contract.

"The contract permits extension of the period for delay in availability of the land by K-RIDE. But L&T has opted to terminate the contract unilaterally and illegally," said the release.

The claims, said K-RIDE, had been referred to the Amicable Settlement Committee, as per the provision of the contract.

The work front available to L&T is about 84 per cent of the total corridor length of C2 and 17 km in C4, said the release.

"However, the progress achieved by L&T so far in C2 and C4 are not commensurate with the available work front, which exposes L&T's failures in carrying out the work, which is citing non-availability of work front as reason," added the press release.

According to K-RIDE, work was delayed because L&T failed to mobilise adequate resources and there was a delay in finalising designs. It also said that the project managers of L&T were frequently changed, affecting the progress of work.

There was no immediate reaction from L&T.

 

(Only the headline and picture of this report may have been reworked by the Business Standard staff; the rest of the content is auto-generated from a syndicated feed.)

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

Topics :L&T Bengalurutransport

First Published: Aug 02 2025 | 10:48 PM IST

Next Story