India Power Production

Kshema Power bags order to build substation for 350 MW hybrid project in MP

Chennai-based engineering firm Kshema Power on Thursday said it has secured an order from Oyster Green Hybrid Three Pvt Ltd to develop a 33 kV/220 kV AIS power substation for a 350 MW wind-solar hybrid project in Madhya Pradesh. Together, the two companies will deliver infrastructure that will enhance clean energy evacuation capacity in one of India's fastest-expanding renewable corridors, a company statement said. According to the statement, under the contract, Kshema Power will undertake the supply, erection, testing, and commissioning of a 51-kilometre transmission line, along with the design, engineering, supply, installation, civil works, testing, and commissioning of an AIS substation. The installation will serve as the backbone of power evacuation for Oyster Green Hybrid Three's hybrid project, enabling efficient and reliable integration of wind and solar power into the grid. The project is expected to be completed by July 2026. Abhinand Basant, Deputy Managing Director, Ksh

Updated On: 11 Dec 2025 | 2:14 PM IST

Power market coupling faces delay, unlikely before December 2027: Report

A J M Financial report says regulatory and procedural hurdles could delay India's proposed power market coupling until late 2027, affecting IEX's market share projections

Updated On: 03 Nov 2025 | 4:51 PM IST

India's Oct power consumption dips 6% to 132 billion units on mild weather

Power consumption in the country fell by 6 per cent to 132 billion units in October from 140.47 BUs in same month last year, mainly on account of less use of cooling appliances. The October month also saw rains in various parts of the country. The decline in power consumption was attributed to unseasonal rainfall during the month in some parts of the country coupled with onset of winter season, which kept temperatures in check, experts said. The peak power demand met during October was at 210.71 GW, lower from 219.22 GW recorded in October 2024. The peak power demand had touched an all-time high of about 250 GW in May 2024. The previous all-time high peak power demand of 243.27 GW was recorded in September 2023. However, this summer (April onwards), the record peak power demand was 242.77 GW in June. Experts said the power demand and consumption are likely to be subdued in November as well due to moderation in temperature levels, which would reduce use of cooling appliances.

Updated On: 01 Nov 2025 | 5:37 PM IST

India's power output growth slows in September as industrial momentum eases

Power output rose 3.2% year-on-year but fell short of August's 4% growth, marking the first monthly drop in three months, according to daily analysis of Grid India data

Updated On: 03 Oct 2025 | 6:37 PM IST

Tariff hikes, lower costs to cut discom losses to ₹8,000-10,000 crore

CRISIL Ratings expects operating losses of state-owned power discoms to drop to Rs 8,000-10,000 crore in FY25, helped by tariff hikes, lower purchase costs and improved efficiency

Updated On: 29 Sep 2025 | 8:32 PM IST

Adani Power rated 'Overweight' by Morgan Stanley; 65% upside in bull case

Morgan Stanley assigned a target of ₹818 per share under the base case, an upside of nearly 30 per cent from Thursday's close

Updated On: 19 Sep 2025 | 11:23 AM IST

Adani Power wins additional 800 MW LoA from MPPMCL, total at 1,600 MW

The project is expected to generate direct and indirect employment of around 9,000-10,000 during the construction phase

Updated On: 11 Sep 2025 | 9:06 AM IST

Manohar Lal, Jitendra Singh review roadmap for 100GW nuclear power goal

Science and Technology Minister Jitendra Singh on Friday discussed the timeline for achieving the 100 GW nuclear power target by 2047 with Power Minister Manohar Lal Khattar. At a meeting in Parliament House, the two ministers and senior officials from the Power Ministry and the Department of Atomic Energy reviewed the roadmap to increase India's nuclear energy capacity from the current 8.8 GW to 22 GW by 2032. The two leaders discussed plans to increase the nuclear power capacity to 49 GW by 2037, scale it up to 67 GW by 2042 and reach the 100 GW target set by Prime Minister Narendra Modi by 2047. Singh highlighted the government's landmark initiative to open the nuclear sector for private sector participation, emphasising its pivotal role in strengthening India's energy security. He said there was a strong and vibrant response from the industry to the Bharat Small Modular Reactor (SMR) programme, leading to an extension of the request for proposal (RFP) submission deadline to ...

Updated On: 08 Aug 2025 | 10:53 PM IST

Coal India allows thermal plants to trade surplus power in open market

Under the previous policy framework, electricity produced using Coal India Ltd's linkage coal could not be traded in the open market, regardless of whether it was surplus

Updated On: 07 Aug 2025 | 5:00 PM IST

Stakeholders must unite to plan emission control in power sector: SC

The Supreme Court has stressed that all stakeholders must be on the same platform to discuss, formulate and implement the plan to address the issue of carbon emissions arising out of power generation. The apex court directed the Ministry of Power to convene a joint meeting with the Central Electricity Authority and the Central Electricity Regulatory Commission to discuss the plan of action with respect to reduction of carbon emissions in power generation sector. A bench of Justices P S Narasimha and A S Chandurkar said it is equally necessary to ensure that policy makers are attuned with ground realities and difficulties of the regulatory and executory machinery. "In order to address the issue of carbon emissions arising out of power generation, we deem it necessary that all stakeholders must be on the same platform to discuss, formulate and implement the plan systematically and consistently for achieving short-term and long-term goals," the bench said in its July 22 order. The top

Updated On: 02 Aug 2025 | 3:02 PM IST

India's daily thermal power output dips to record 62% low, RE's share rises

Share of core renewables touches a high of 17% for the first time, according to official data

Updated On: 17 Jul 2025 | 12:27 PM IST

Govt extends NTPC CMD Gurdeep Singh's tenure by one year till July 2026

The government has extended the tenure of Gurdeep Singh as Chairman and Managing Director (CMD) of NTPC by one year, an official notification said. Singh who was due to retire on July 31, will now lead the power giant for till July-end 2026. NTPC is India's largest power producing entity under Ministry of Power. The Appointments Committee of the Cabinet (ACC) has approved the proposal of the Ministry of Power for re-employment of Shri Gurdeep Singh as Chairman and Managing Director (CMD), NTPC (India) Limited on contract basis for a period of one year beyond the date of his superannuation i.e. w.e.f. 01.08.2025 till 31.07.2026, the Department of Personnel & Training said in a notification. In May, the government headhunter PESB found none of the dozen candidates suitable for the role of chairman and managing director of India's biggest power producer NTPC, as its string of struggle in finding the right candidates for top job at PSUs continued. The Public Enterprise Selection Board

Updated On: 17 Jul 2025 | 10:55 AM IST

Groww rolls out BSE Power ETF, FoF amid India's surging electricity demand

Both schemes are benchmarked to the BSE Power Index - Total Return Index (TRI), offering exposure to a diversified basket of companies engaged in power generation, transmission, utilities, and infra

Updated On: 14 Jul 2025 | 12:56 PM IST

Power projects with ₹1 trn investment underway in Arunachal: CM Pema Khandu

Multiple hydro-power projects with an investment of over Rs one lakh crore are underway in Arunachal Pradesh to produce 18,000 MW of power, Chief Minister Pema Khandu has said. Five of these projects of 2,620 MW have been allocated by the state government to the North Eastern Electric Power Corporation Ltd (NEEPCO), five projects of 5,097 MW to Satluj Jal Vidyut Nigam Ltd (SJVN) and two projects with a capacity of 3,800 MW to the National Hydroelectric Power Corporation (NHPC). "As of now, on the ground, the work for generating a total of 18000 MW of hydro-power is on. In the coming days, we will add more projects. All these projects involved more than Rs 1 lakh crore investment," Khandu told PTI in an interview here. He said these projects were earlier allotted to private sector developers but remained non-starters due to various reasons. The Arunachal Pradesh government, therefore, decided to rope in central hydro PSUs to give a push to the languishing projects. "These projects .

Updated On: 13 Jul 2025 | 11:13 AM IST

Nearly half of India's power generation capacity non-fossil: Govt data

Nearly half of India's installed power generation capacity of a total of 476 GW is non-fossil fuel-based as of June, but coal-based thermal electricity plays a critical part, according to government data. According to a government explainer on energy and environment issued on Sunday, India's total installed power capacity has reached 476 GW as of June 2025. Non-fossil fuel sources now contribute 235.7 GW (49%) of total capacity, including 226.9 GW renewable and 8.8 GW nuclear, it stated. As of June 2025, India's renewable energy includes 110.9 GW of solar and 51.3 GW of wind power installed capacity. In addition to the installed capacity, 176.70 GW worth of RE projects are under implementation, with 72.06 GW under bidding stages. It explained that thermal power remains dominant, accounting for 240 GW or 50.52 per cent of installed capacity. It noted that India's energy sector is heavily reliant on non-renewable thermal sources, which together account for the largest share of the

Updated On: 22 Jun 2025 | 2:28 PM IST

PM Modi to inaugurate development projects worth Rs 48,520 crore in Bihar

Prime Minister Narendra Modi will inaugurate and lay foundation stone of multiple development projects worth over Rs 48,520 crore in Bihar's Karakat on Friday. The PM, who arrived in Patna on a two-day visit to the state on Thursday, will also address a public rally in Karakat. According to an official communication, "The PM will inaugurate, lay foundation stone and dedicate to the nation multiple development projects worth over Rs 48,520 crore in Karakat. Boosting power infrastructure in the region, he will lay the foundation stone for the Nabinagar Super Thermal Power Project, stage-II (3x800 MW) in Aurangabad district worth over Rs 29,930 crore, which will aim at ensuring energy security for Bihar and eastern India". It will boost industrial growth, create job opportunities, and provide affordable electricity in the region, it added. Further, in boost to the road infrastructure and connectivity in the region, the PM will lay the foundation stone for various road projects includi

Updated On: 30 May 2025 | 10:06 AM IST

Govt trims gas-based power generation capacity to 20.13 GW as of April

The country has reduced gas-based power generation capacity by 20 per cent or 5 GW in the last three months to 20.13 gigawatt (GW) as of April. The development comes at a time when the government has issued a directive to use unutilised gas-based generation capacity to ensure uninterrupted power supply during the summer season, when projected demand is expected to hit 277 GW. According to Central Electricity Authority (CEA) data, India's overall installed power generation capacity was 472.468 GW in April, while the share of gas-based capacity was at 20.13 GW. In March, the total power generation was at 475.211 GW and the share of gas-based capacity was at 24.53 GW. India's overall installed power generation capacity was at 470.448 GW in February and the share of gas-based capacity was at 25.18 GW. The power ministry has decided to use unutilised gas-based electricity generation capacity to ensure uninterrupted power supply and maintain grid security amid an anticipated rise in the

Updated On: 21 May 2025 | 10:55 AM IST

Policy dialogue crucial to boost pumped storage projects: Power secy

There is a need for policy dialogues to fast-track development of pumped storage hydroelectricity projects in the country with a focus on reviewing procedural delays in such projects, Power secretary Pankaj Agarwal said on Thursday. The senior ministry official was addressing a 'Brainstorming Session on Pumped Storage Projects: Powering India's Renewable Future' organised by THDC India and Central Electricity Authority in association with NTPC in the national capital. In his address, Agarwal emphasised ensuring grid stability is a matter of urgent national priority and every state must actively contribute to this effort. "The secretary also said that there is a need of brainstorming and policy dialogue to fast-track PSP development, with a focus on reviewing procedural delays and streamlining processes and platforms like these are vital for building consensus and enabling coordinated sectoral action," THDC India said in a statement. He also emphasised that ensuring grid stability i

Updated On: 01 May 2025 | 8:35 PM IST

THDC synchronises first unit of 1,000 MW Tehri pumped storage project

State-owned THDC India on Thursday announced synchronisation of the first 250 MW unit of its pumped storage plant (PSP) in pump condenser mode at Tehri in Uttarakhand. In pump condenser mode of operation, the turbine is used to generate electricity and simultaneously as a condenser or a heat exchanger. THDC India is constructing a 1,000-MW (250 MW X 4 units) PSP project at Tehri. "CMD R K Vishnoi has announced achievement towards successful commissioning of India's first variable speed 1,000 MW PSP at Tehri with the successful synchronisation of its first unit (of 250 MW) to the Indian grid in pump condenser mode," THDC India said in a statement. The synchronisation took place on Wednesday. With the completion of this pumped storage project, the tehri hydro power complex will have a total installed capacity of 2,400 MW. The company is currently operating 1,000-MW Tehri HPP (hydro power project) and 400-MW Koteshwar HEP (hydro electric power). Based in Rishikesh, Uttarakhand, THD

Updated On: 24 Apr 2025 | 8:21 PM IST

Steps taken for meeting 277 GW peak power demand in FY26: Shripad Naik

The government has taken steps to ensure uninterrupted power supply and meet the projected peak power demand of 277 GW in 2025-26, Union Minister Shripad Naik said on Thursday. The All India Peak Demand for 2024-25 (till February) was 249.856 GW, registered on May 30, 2024. However, this peak demand was successfully met with only a marginal gap of 2 MW, the Minister of State for Power said in a reply to the Lok Sabha. In 2025-26, Naik said a peak demand of 277 GW is expected as per the mid-term review of the 20th Electric Power Survey. "The country is confident to meet this projected demand with optimal usage of existing and under construction capacities," he said. Besides, all power generation companies, including independent power producers (IPPs) and central generating stations, have been advised to generate and maintain full availability on a daily basis, excluding the period of planned maintenance or forced outage. Planned maintenance of generating units is being minimised .

Updated On: 27 Mar 2025 | 9:00 PM IST