Nearly 65% of infrastructure projects delayed by Covid-induced lockdowns

Of these projects, 438 reported cost overruns and 218 had both time and cost overruns, showed a flash report on central sector projects released by MoSPI

Infrastructure, DFI, workers, contruction, realty, real estate, property, workers, labour
premium

Photo: Workers at an infrastructure project

BS Reporter New Delhi
As many as 563 central sector infrastructure projects, comprising 65 per cent of the total 862 having definite timelines, were running behind schedule as on October 1 this year due to Covid-induced lockdowns in states and delays in land acquisition among  other factors, official data showed. The projects taken up for monitoring cost at least Rs 150 crore.

On the other hand, only 287 projects, accounting for 33 per cent of the total, had time overruns. Only 12 projects were ahead of schedule.

While there were a total 1,670 projects, the year of commission was not available for 808. In fact, the