Reduce construction disputes to accelerate India's infrastructure roll-out
It is important to demystify the conundrum of construction disputes, so that India can accelerate its infrastructure growth and wasteful disputes are avoided
Ranjit PrakashAnshuman Pande B2B Connect | Mumbai
)
It is somewhat of a contradiction, therefore, that while most project contracts identify causes and provide for mechanisms to deal with delays, legal disputes between developers and executing agencies (contractors) related to time overruns appear to have been increasing over the past few years. These rising incidences have serious time and cost implications, not only for these two sets of parties, but also for the project at large. It is, thus, important to demystify the conundrum of construction disputes, so that India can accelerate its infrastructure growth and wasteful disputes are avoided.
The genesis of such disputes is usually the delay clause in the contract itself – which imposes stiff legal ramifications upon the party responsible for the delay. Such defaulting party would not only be barred from claiming its contractual remedies for delay (which include monetary compensation, the power to disengage from the contract, compensation for special losses and the like), but may also become legally liable to the other party for recompense of losses. Losses involving goodwill and reputation, as well as the possibility that the future of the project may be seen to be in jeopardy, would, in any case, be grievous in the event of a contractual default.
Also Read
Moreover, in the absence of clarity on causes of the delay, at times one or both parties do not even formally acknowledge the incidence of a delay and hope that the work continues unabated into delayed time. They often postpone resolution of critical questions, such as:
- What are the revised timelines for the works? If not, the timeline may be legally deemed to be open-ended and loose, leaving both sides unsure as to the longevity of the project construction;
- What is the effect of the delay over the remaining works and how would both parties apportion the responsibility to meet the same? This is an important question, especially if such delays lead to a domino effect and cause further overruns;
- How would cost overruns be met once the works are carried out into delayed time? How would escalated costs of resources, to take one example, be revised, especially in cases of fixed price or lump-sum contracts?
- If the cause of the delay is contentious, should a party even continue with the project, especially if the other party is shifting blame? The other party is unlikely to change its stand once issues escalate towards a legal dispute.
It is, therefore, vital that clauses in the contract should be carefully drafted. This would ensure that in the event of an overrun, there are provisions for fresh timelines and the risks and responsibilities of each party can be exhaustively defined, without much ambiguity. The clauses should also provide for protocols and mechanisms for deciding the way ahead. Delay analysis should be exhaustive and objective – possibly coupled with a sign-off from a pre-agreed, independent party acceptable to both sides.
If disputes still arise, then parties should take a call on their remedies expeditiously rather than stalling the resolution of issues that would affect the project’s progress and their own legal/contractual recourses.
Finally, the need of the hour is honest and transparent dealing between the parties to a project contract – not only through careful contract mechanisms, but also by realistic project management. While it is undeniable that external factors beyond control of both parties do play a major role in delays, the developers and contractors do not help the situation by hurling charges, hiding behind opaque clauses and relying upon reams of paper trails. Such actions only delay the project construction further and most often end up in courts or dispute-resolution forums.
________________________________________________________________________________________________
Ranjit Prakash is the senior partner at HSA Advocates
Anshuman Pande is the senior associate at HSA Advocates
More From This Section
Don't miss the most important news and views of the day. Get them on our Telegram channel
First Published: May 30 2015 | 2:50 PM IST

