Severe delays in Rs 1 trillion national highway projects: CareEdge Ratings

Delayed HAM projects rose from 33% of total projects to 55%, says agency

Highway, Road
(Photo: Shutterstock)
Dhruvaksh Saha New Delhi
3 min read Last Updated : Feb 07 2025 | 7:18 PM IST
Adding to the government’s woes with delays in infrastructure projects, more than Rs 1 trillion worth of national highway projects awarded under the Hybrid Annuity Model (HAM) have been experiencing severe delays, rating agency CareEdge Ratings said on Friday.
 
“CareEdge Ratings forecasts a nearly 7-10 per cent decline in the pace of national highway construction in FY25 compared to FY24. The construction rate is expected to slow from 12,350 km in FY24 to 11,100-11,500 km in FY25, closer to nearly 31 km per day,” it said.
 
In the report, the agency conducted an extensive analysis of 374 HAM projects awarded by the National Highways Authority of India (NHAI) between 2015 and 2024.
 
“These projects span an aggregate length of approximately 16,000 km and have a total bid project cost (BPC) exceeding Rs 4.03 lakh crore. As of the end of September 2024, 42 per cent of the sample BPC, aggregating over Rs 1.65 lakh crore, had been commissioned, while around 45 per cent of the projects, aggregating over Rs 1.80 lakh crore, are in the construction phase, and the remaining 13 per cent are awaiting the appointed date to commence construction,” it said.
 
According to the agency, 55 per cent of the analysed projects have been delayed beyond six months. In June 2023, this proportion was only 33 per cent, signalling a rise in delays in highway construction. While the grant of an extension of time (EOT) mitigates project-specific risks to an extent, it impacts the overall construction pace and the profitability of road developers, CareEdge said.
 
“Revenue visibility of major road developers has been impacted by the diminished pace of NHAI project awards and pending construction commencement for a large chunk of projects. Operating profitability is estimated to steadily decline by 200 basis points in FY25 from FY23 levels, led by increased competition and high overheads. Furthermore, with the discontinuation of the Atma Nirbhar Bharat scheme for releasing monthly payments, the working capital cycle is expected to increase by around 15-20 days. Nevertheless, comfortable leverage and a strong capital structure impart resilience to the credit profile of major road developers. Players with a pool of operational assets shall be better positioned to manage their leverage and liquidity,” said Setu Gajjar, assistant director at the rating agency.
 
The primary reasons behind these delays are a standard construction period of two years regardless of project complexities, heightened competitive intensity, non-availability of hindrance-free right of way, and excessive rainfall.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

Topics :National HighwayroadsHighwaysHybrid annuity model

First Published: Feb 07 2025 | 7:18 PM IST

Next Story