NTPC to operationalise 800 Mw at Odisha's Darlipalli power plant in FY19

"The commissioning activities of 800 Mw are going on. The unit will be operational in the current financial year", said a senior NTPC official

NTPC
premium

NTPC

Nirmalya Behera Bhubaneswar
Country’s largest thermal power producer NTPC Ltd plans to operationalise 800 Mw of its 1600 Mw (2x800) supercritical coal-based power plant at Darlipalli in Odisha's Sundergarh in the current financial year.

“The commissioning activities of 800 Mw are going on. The unit will be operational in the current financial year”, said a senior NTPC official.

By September 2019, the full capacity of 1600 Mw is projected to start producing power. The total cost of the project is pegged at Rs 125 billion.Odisha will get 50 per cent power of the total capacity.

The power major will source coal from its