You are here: Home » Companies » News
Business Standard

R-Power's tariff earnings hinge on commission date

Jyoti Mukul  |  New Delhi 

The problems for Reliance Power's (R-Power's) Sasan plant in Madhya Pradesh, the country's first ultra mega power project (UMPP), based on domestic coal, does not seem to end, even as it has commenced operations. The Western Regional Load Despatch Centre (WRLDC), the transmitter of power, has disputed R-Power's claims on the date of the plant's commissioning.

WRLDC has petitioned the Central Electricity Regulatory Commission (CERC), questioning a certificate from an independent engineer for the performance test conducted to declare commissioning of the Sasan UMPP. This could impact the tariff R-Power-controlled Sasan Power Ltd would earns from sale of power.

R-Power had produced the test certificate claiming March 30, 2013, as the date of commissioning. If this certificate is taken as the basis, the first year of operation for the plant will be 2012-13, during which it gets about 70 paise a unit (kilowatt per hour) for the power supplied, says a government official asking not to be named. The same tariff is to continue for the second year but it is to rise more than 70 per cent from the third year. If 2012-13 is not considered the first year, the third year - as also a higher rate of tariff for the company - gets pushed by another year.

The electricity generated from the project would be sold to 14 distribution across seven states, including Madhya Pradesh, Uttar Pradesh, Punjab and Delhi.

R-Power did not respond to email queries. But on April 4 it had issued a statement announcing the commissioning of its first 660-Mw unit at the Sasan UMPP on March 30. This is the largest integrated power plant and coal mining project in the world, with an estimated investment of over Rs 23,000 crore.

According to clause 6.3.1 (a) and (b) of the power purchase agreement (PPA), the commissioning test should have been carried out in accordance with Schedule 5 of PPA and the result of the test should not have been less than 95 per cent of its contracted capacity. The WRLDC plea contends, the test result is not in accordance with the clause and, therefore, not acceptable.

In its arguments before CERC, WRLDC said Sasan Power was "indulging in intentional misdeclaration of parameters related to commercial mechanism" and had "purported to declare de-rated capacity of 101.38 Mw as commercial on the grounds of load restriction" imposed by the despatch centre. The order on admissibility of the petition would come within a fortnight, CERC Chairman Pramod Deo told Business Standard.

He said CERC wanted to decide on the WRLDC petition early, since that would fix the date of commissioning. That would have an impact on yet another petition filed by R-Power seeking compensation for loss of revenue and impact on cost of operation due to change of law.



A PETITION WAR

* R-Power says the first 660-Mw unit commissioned on March 30, 2013
* WRLDC petition to CERC disputes commissioning date
* Three petitions have been filed by R-Power seeking compensation
* Power is to be sold to seven states at levelised tariff of Rs 1.196/kwh
* CAG has estimated tariff collection of Rs 87,749 cr over 25 years
* Sasan UMPP's total capacity will be 3,960 Mw

Dear Reader,


Business Standard has always strived hard to provide up-to-date information and commentary on developments that are of interest to you and have wider political and economic implications for the country and the world. Your encouragement and constant feedback on how to improve our offering have only made our resolve and commitment to these ideals stronger. Even during these difficult times arising out of Covid-19, we continue to remain committed to keeping you informed and updated with credible news, authoritative views and incisive commentary on topical issues of relevance.
We, however, have a request.

As we battle the economic impact of the pandemic, we need your support even more, so that we can continue to offer you more quality content. Our subscription model has seen an encouraging response from many of you, who have subscribed to our online content. More subscription to our online content can only help us achieve the goals of offering you even better and more relevant content. We believe in free, fair and credible journalism. Your support through more subscriptions can help us practise the journalism to which we are committed.

Support quality journalism and subscribe to Business Standard.

Digital Editor

First Published: Wed, May 29 2013. 00:57 IST