The Centre will soon offer 44 new power transmission projects worth Rs 41,369 crore with most projects under the ‘Green Energy Corridors’ (GEC) plan.
These projects would evacuate close to 38 Gw of renewable energy from the Western and Northern parts. Such a large scale of transmission projects under the bidding mode has been offered after a hiatus of at least three years.
GEC is an alternative transmission system for renewable energy (RE) power projects. The first phase of GEC was constructed by state-owned Power Grid Corporation of India (PGCIL). Bulk of the projects from the second phase were awarded through competitive bidding.
While the earlier two phases aimed at transmission of 175 Gw of RE power, the upcoming phases are for realisation of 450 Gw of RE in this decade, said sector executives.
The upcoming round of project tenders could see participation from leading companies such as Adani Transmission, which plans to increase its green footprint, Sterlite Power, which is IPO bound, and new companies such as ReNew Power, which is expanding into transmission from power generation.
PGCIL also participated in the competitive bidding and the Navratna PSU is shifting gears towards RE connectivity and intra-state projects.
The National Committee of Transmission (NCT), formed by the ministry of power, approved these projects to be offered under the ‘tariff-based competitive bidding’ (TBCB). The projects are part of the Centre’s flagship programme of GEC, which aims at connecting renewable energy projects or zones with the national grid.
The proposal, which was approved, has three segments. They are: GEC III for the Western region, which has projects worth Rs 14,388 crore to evacuate 15 Gw of RE and GEC III Northern region with Rs 26,465 crore of projects to transfer 20 Gw of RE power. The third tranche of projects is outside the gamut of the GEC corridor.
These projects would evacuate close to 38 Gw of renewable energy from the Western and Northern parts. Such a large scale of transmission projects under the bidding mode has been offered after a hiatus of at least three years.
GEC is an alternative transmission system for renewable energy (RE) power projects. The first phase of GEC was constructed by state-owned Power Grid Corporation of India (PGCIL). Bulk of the projects from the second phase were awarded through competitive bidding.
While the earlier two phases aimed at transmission of 175 Gw of RE power, the upcoming phases are for realisation of 450 Gw of RE in this decade, said sector executives.
The upcoming round of project tenders could see participation from leading companies such as Adani Transmission, which plans to increase its green footprint, Sterlite Power, which is IPO bound, and new companies such as ReNew Power, which is expanding into transmission from power generation.
PGCIL also participated in the competitive bidding and the Navratna PSU is shifting gears towards RE connectivity and intra-state projects.
The National Committee of Transmission (NCT), formed by the ministry of power, approved these projects to be offered under the ‘tariff-based competitive bidding’ (TBCB). The projects are part of the Centre’s flagship programme of GEC, which aims at connecting renewable energy projects or zones with the national grid.
The proposal, which was approved, has three segments. They are: GEC III for the Western region, which has projects worth Rs 14,388 crore to evacuate 15 Gw of RE and GEC III Northern region with Rs 26,465 crore of projects to transfer 20 Gw of RE power. The third tranche of projects is outside the gamut of the GEC corridor.

)