Highway projects on roll again
NHAI awards 13 contracts after a year-long lull

| After a lull of nearly a year, the National Highway Authority of India (NHAI) is back in action. It awarded 13 contracts in April alone for the second phase of the National Highway Development Programme (NHDP). | |||
| The authority had given contracts worth Rs 1,900 crore for various stretches of roads forming the North-South and East-West (NS-EW) corridors totalling 422.47 km during the month, an NHAI official told Business Standard. | |||
| These 13 awards bring the total count of contracts awarded in this financial year to 21, including six Phase III stretches on build-operate-transfer (BOT) basis which had been pending since November 2003 and two others under the NS-EW corridor. | |||
| The flurry of contracts comes after a year-long hiatus. No contract had been awarded since the change of government in May last year. | |||
| The approvals for the six Phase III contracts covering 10,000 km was received from the Centre only in March, 2005. | |||
| For the NS-EW Corridor, the projected investment did not materialise as the NHAI did not award any new contracts during the period. | |||
| "After projecting market borrowings of Rs 3,300 crore during 2004-05 on the expectation that some progress on the Phase-II would be achieved, we ended up not tapping the markets at all during the year," an official said. | |||
| In the past year, the authority was busy fine-tuning the terms of concession agreement to correct the anomalies that were found during the first phase of NHDP. | |||
| Local residents had complained of lack of planning for the flyovers and bypasses being built, officials said. | |||
| Work on the ground, however, progressed well. The stretches in the Golden Quadrilateral, for which contracts were awarded before May 2004, were completed at a faster rate. | |||
| During May 2004-April 2005, about 5.98 km of roads were widened every month as against 4.5 km per a month during the preceding 11-month period. | |||
| This acceleration was mainly due to the nature of work involved. Construction during the initial phases was slower as it involved time-consuming activities like land acquisition, seeking permissions from various agencies and digging up of land. In the later stages, only surfacing was required. | |||
| Another crucial factor is the bunching of contracts. If a number of contracts were awarded at the same time, the progress recorded was outstanding in terms of construction but zero in terms of completed sections, an official explained. | |||
| "On the other hand, bunching a large number of contracts nearing completion may give an impression of good progress," he said. | |||
|
| |||
More From This Section
Don't miss the most important news and views of the day. Get them on our Telegram channel
First Published: May 17 2005 | 12:00 AM IST

