Thursday, November 26, 2026 | 05:44 PM ISTहिंदी में पढें
Business Standard
Notification Icon
userprofile IconSearch

Infra projects see cost overrun of ₹3.28 trillion in October: MoSPI

Government data show 1,862 infrastructure projects have a revised cost of ₹38.11 trillion, up from ₹34.83 trillion, with a cumulative cost overrun of ₹3.28 trillion.

infrastructure, municipal bonds

India’s infrastructure project pipeline has recorded a cumulative cost overrun of ₹3.28 trillion, with transport and logistics accounting for the largest share of ongoing projects, according to MoSPI data. | Image:Bloomberg

Press Trust of India

Listen to This Article

Infrastructure projects worth more than ₹0.0015 trillion each recorded a cumulative cost overrun of approximately ₹3.28 trillion, according to a monthly government report for October 2026.
 
About 1,862 ongoing infrastructure projects across 17 central ministries and departments were monitored. The total revised cost was ₹38.11 trillion, compared with the original cost of ₹34.83 trillion.
 
However, the report did not specify the actual number of projects that faced cost overruns.
 
The cumulative expenditure incurred on these projects stood at ₹17.87 trillion, accounting for approximately 46.88 per cent of the project cost and indicating steady progress in project implementation, the Ministry of Statistics and Programme Implementation (MoSPI) said in its monthly report for October on Wednesday.
 
 
A significant proportion of projects are at advanced stages, with 649 projects (35 per cent) having achieved over 80 per cent physical progress, while 326 (18 per cent) have crossed 80 per cent financial completion.
 
The data also reflects a balanced pipeline, with projects distributed across early and advanced stages of implementation.
 
Of the 1,862 ongoing infrastructure projects, 790 are mega projects, with a project cost of ₹0.01 trillion or more, and 1,072 are major projects, with a cost below ₹0.01 trillion.
 
The transport and logistics sector accounts for the highest number of ongoing projects (1,324), with a cumulative cost of ₹20.37 trillion, underscoring the priority given to connectivity-driven infrastructure growth.
 
The report said physical and financial progress broadly move in tandem, with a large number of projects clustered at the initial (0-20 per cent) and advanced (81-100 per cent) stages, indicating a pipeline of newly started projects alongside many nearing completion.
 
While physical progress exceeds financial advancement in the 81-100 per cent range, financial progress is relatively higher in the early stages, reflecting upfront expenditure patterns in project implementation.
 
The Ministry of Road Transport and Highways accounts for the highest number of projects, at 972 (52 per cent of the total 1,862), and a share of the total revised project cost of ₹9.55 trillion (25 per cent of the total project cost of ₹38.11 trillion), highlighting its central role in national infrastructure development.
 
The Ministry of Railways has 288 ongoing projects (15 per cent), with a total revised project cost of ₹7.38 trillion (19 per cent).
 
The Coal Ministry accounts for 121 ongoing projects (7 per cent), with a total revised project cost of ₹2.22 trillion (6 per cent).
 
The Ministry of Petroleum and Natural Gas, Ministry of Power, Ministry of Housing and Urban Affairs, and the Department of Water Resources, River Development & GR are implementing 117, 108, 50 and 33 projects, respectively, with associated project costs of ₹4.42 trillion, ₹6.55 trillion, ₹3.44 trillion and ₹1.93 trillion.
 
The remaining 173 projects (9 per cent), with a total project cost of ₹2.63 trillion (7 per cent), are distributed across various ministries and departments, including Higher Education, Civil Aviation, Steel, Telecommunications, Labour and Employment, Ports, Shipping and Waterways, Health and Family Welfare, Mines, DPIIT and Sports.

Don't miss the most important news and views of the day. Get them on our Telegram channel

First Published: Nov 26 2026 | 5:20 PM IST