Tata Power Company completes uprating of 220kV Kalwa-Salsette line

For bringing power to Mumbai City
Tata Power Company has completed the uprating of existing transmission line no. 4 between MSETCL Kalwa Receiving Station and Tata Power Salsette Receiving Station (8 km route length) by replacing existing conductor with high ampacity conductor (capacity increased from 900 amps to 1800 amps). The uprated 220kV line will relieve critical loading of the Kalwa Salsette lines and will enhance firm transmission capacity for bringing power from outside to Mumbai City.Powered by Capital Market - Live News
More From This Section
Don't miss the most important news and views of the day. Get them on our Telegram channel
First Published: Dec 17 2015 | 3:45 PM IST