NHPC's Subansiri project cost may double to Rs 12,000 cr

Country's largest hydro power producer, NHPC executing 2,000-MW Subansiri hydel plant in Assam

The total cost of state-owned NHPC's project in is likely to be around Rs 12,000 crore, nearly double than envisaged initially, following delays on account of various hindrances.

The country's largest producer, is executing the 2,000-MW Subansiri in Assam. The original cost of the project was Rs 6,285 crore.

"Local issues, contractual issues, geological surprises, delay in decision making and poor risk-taking assessment have impacted the progress on the Subansiri project, which is now likely to cost nearly Rs 12,000 crore," a senior company official told PTI.

The project has been stalled since December 2011, after the local people raised issues related to its safety and downstream impact.

"Assam also wanted to increase its total share of power from the project," the official said, adding that the state was earlier granted 208 MW of electricity from the hydel station which has now increased to 300 MW.

Besides, the state is expected to get 25 MW or more free power from the plant which is likely to resume construction work next month. The project, earlier expected to be fully commissioned by December 2012, is now likely to be operational by December 2017.

"We are hopeful that the construction work on the project would start again from December, next month," the official said.

According to sources, the had a meeting with the state government earlier this month and achieved some breakthrough on the issues.

Once commissioned, Subansiri (250x8) will be India's biggest hydroelectric project. The project is located near North Lakhimpur on the border of Assam and Arunachal Pradesh.

The estimated annual energy generation from the project is 7,421 million units.

NHPC generates 5,702 MW electricity from 17 hydel stations in the country. As many as seven power stations with total capacity of 4,095 MW are under construction.

image
Business Standard
177 22
Business Standard

NHPC's Subansiri project cost may double to Rs 12,000 cr

Country's largest hydro power producer, NHPC executing 2,000-MW Subansiri hydel plant in Assam

Press Trust of India  |  New Delhi 



The total cost of state-owned NHPC's project in is likely to be around Rs 12,000 crore, nearly double than envisaged initially, following delays on account of various hindrances.

The country's largest producer, is executing the 2,000-MW Subansiri in Assam. The original cost of the project was Rs 6,285 crore.



"Local issues, contractual issues, geological surprises, delay in decision making and poor risk-taking assessment have impacted the progress on the Subansiri project, which is now likely to cost nearly Rs 12,000 crore," a senior company official told PTI.

The project has been stalled since December 2011, after the local people raised issues related to its safety and downstream impact.

"Assam also wanted to increase its total share of power from the project," the official said, adding that the state was earlier granted 208 MW of electricity from the hydel station which has now increased to 300 MW.

Besides, the state is expected to get 25 MW or more free power from the plant which is likely to resume construction work next month. The project, earlier expected to be fully commissioned by December 2012, is now likely to be operational by December 2017.

"We are hopeful that the construction work on the project would start again from December, next month," the official said.

According to sources, the had a meeting with the state government earlier this month and achieved some breakthrough on the issues.

Once commissioned, Subansiri (250x8) will be India's biggest hydroelectric project. The project is located near North Lakhimpur on the border of Assam and Arunachal Pradesh.

The estimated annual energy generation from the project is 7,421 million units.

NHPC generates 5,702 MW electricity from 17 hydel stations in the country. As many as seven power stations with total capacity of 4,095 MW are under construction.

RECOMMENDED FOR YOU

NHPC's Subansiri project cost may double to Rs 12,000 cr

Country's largest hydro power producer, NHPC executing 2,000-MW Subansiri hydel plant in Assam

The total cost of state-owned NHPC's Subansiri project in Assam is likely to be around Rs 12,000 crore, nearly double than envisaged initially, following delays on account of various hindrances The total cost of state-owned NHPC's project in is likely to be around Rs 12,000 crore, nearly double than envisaged initially, following delays on account of various hindrances.

The country's largest producer, is executing the 2,000-MW Subansiri in Assam. The original cost of the project was Rs 6,285 crore.

"Local issues, contractual issues, geological surprises, delay in decision making and poor risk-taking assessment have impacted the progress on the Subansiri project, which is now likely to cost nearly Rs 12,000 crore," a senior company official told PTI.

The project has been stalled since December 2011, after the local people raised issues related to its safety and downstream impact.

"Assam also wanted to increase its total share of power from the project," the official said, adding that the state was earlier granted 208 MW of electricity from the hydel station which has now increased to 300 MW.

Besides, the state is expected to get 25 MW or more free power from the plant which is likely to resume construction work next month. The project, earlier expected to be fully commissioned by December 2012, is now likely to be operational by December 2017.

"We are hopeful that the construction work on the project would start again from December, next month," the official said.

According to sources, the had a meeting with the state government earlier this month and achieved some breakthrough on the issues.

Once commissioned, Subansiri (250x8) will be India's biggest hydroelectric project. The project is located near North Lakhimpur on the border of Assam and Arunachal Pradesh.

The estimated annual energy generation from the project is 7,421 million units.

NHPC generates 5,702 MW electricity from 17 hydel stations in the country. As many as seven power stations with total capacity of 4,095 MW are under construction.
image
Business Standard
177 22

More News

  • Photo: Wikipedia Centre to set up fodder farms in districts
  • People rest next to stacked sacks of onions at a wholesale vegetable market in New Delhi Maharashtra govt proposes subsidy for onion farmers
Widgets Magazine

Widgets Magazine

Upgrade To Premium Services

Welcome User

Business Standard is happy to inform you of the launch of "Business Standard Premium Services"

As a premium subscriber you get an across device unfettered access to a range of services which include:

  • Access Exclusive content - articles, features & opinion pieces
  • Weekly Industry/Genre specific newsletters - Choose multiple industries/genres
  • Access to 17 plus years of content archives
  • Set Stock price alerts for your portfolio and watch list and get them delivered to your e-mail box
  • End of day news alerts on 5 companies (via email)
  • NEW: Get seamless access to WSJ.com at a great price. No additional sign-up required.
 

Premium Services

In Partnership with

 

Dear Guest,

 

Welcome to the premium services of Business Standard brought to you courtesy FIS.
Kindly visit the Manage my subscription page to discover the benefits of this programme.

Enjoy Reading!
Team Business Standard