Foreign Lenders Want To End Dabhol Pact

Slow progress in project restructuring forces lenders to take decision
In a major blow to efforts by the domestic lenders to restart the first phase of the Dabhol power project, overseas lenders to the project have expressed their intention to terminate the power purchase agreement (PPA) with the Maharashtra State Electricity Board (MSEB).
More From This Section
Don't miss the most important news and views of the day. Get them on our Telegram channel
First Published: Apr 04 2003 | 12:00 AM IST