Also Read
Officials reconfirmed the damage to the mangroves near the project site was proven by satellite data but they now said there was no proof that project was to blame. This finding was approved by Javadekar and the Rs 200 crore penalty was dropped.
In its reply to the show-cause notice, on the imposition of the penalty, Adani Ports & SEZ argued “any substantially reduced amount voluntarily keeping in mind our CSR contributions as well as challenges faced by the infrastructure sector in the current economic scenario” be imposed.
The Narain committee had recommended cancellation of clearance to the north port. Instead, while extending clearance to the rest of the project, the ministry decided Adani Ports & SEZ could reapply at a later stage for clearance to the north port.
The ministry had also earlier concluded environmental clearance for phase II of the thermal power plant in the project be cancelled for violating norms. This decision was reversed.
While the idea of the penalty had been dropped before, other changes in the ministry’s views came with joint secretary Bishwanath Sinha assuming charge of the section dealing with the Adani Ports & SEZ file. Sinha in a note on March 2015 wrote, “It is prudent that the environmental clearance granted should not be cancelled for any infrastructure activity, including that of the north port.” He recommended further studies to assess the damage and how it could be fixed.
The then environment secretary Ashok Lavasa said the minister should decide if he would like to hear the project developer personally before deciding on the matter.
Javadekar’s personal secretary wrote the minister wanted to know “if all the points raised in the proponents’ representations have been addressed adequately”. He also asked “on what basis the comparative geo-mapping of 2005-2011 has been carried out”.
The geo-mapping had been undertaken to study damage to mangroves. Sinha replied, “It is not possible to clearly establish whether such changes took place before 2007, when the land came in possession of the project proponent, or the period after. The decision of the committee to capture the satellite data from 2005 is also not explained in the report of the committee. Hence, it is not possible to clearly substantiate the observation and responsibility of project proponent.”
Sinha suggested that the north port, the site at which the damage had taken place, be separated to be dealt with later and not rejected. He added further studies were required to assess the damage and that the biodiverse areas already being used for development be left out of any conservation area demarcated in future.
Susheel Kumar, special secretary at the time, said as studies for damage were to be conducted in future, the costs could not be estimated at the moment. Future studies could decide if the clearance granted to the thermal power plant should continue. Lavasa said the study should not decide the fate of the thermal power plant’s phase-II but only be considered for its subsequent expansions.
In September 2015, the ministry did away with the demand for Rs 200 crore. It deferred a decision on the north port. It decided that if any violations of regulations had been committed they would be examined later independently. Another strategic impact assessment study done later would help “suggest future corrective actions as well as the guiding tool on extension and addition of the capacities.”
Subsequently, the thermal power plant’s phase II also secured clearance.
The ministry has now proposed retrospective clearance and condoning green violations, which could come to the Adani project’s rescue in case violations are determined in future independent investigations proposed by the ministry.