S.No
Project
Project Cost
(i)
Multipurpose General Cargo Berth at Berth No. 5 & 6
Also Read
Rs. 245 Cr.
(ii)
Coal Handling Terminal at Berth No. 7
Rs. 406 Cr.
The nature of agreement and main clauses under the PPP
S.No.
Project
Nature of Agreement
Main Clause
(i)
Multipurpose General Cargo Berth at Berth No. 5 & 6
License Agreement
i. Minimum Guarantee Throughput (MGT) of 5 MMTPA effective from 66th month onwards from the date of handing over of the Licensed Premises.
ii. Revenue share of 18% on gross revenue.
(ii)
Coal Handling Terminal at Berth No. 7
Concession Agreement
i. MGT fixed for the concessionaire is as under:
Year 1 0.8 MMTPA
Year 2 1.1 MMTPA
Year 3 1.4 MMTPA
Year 4 1.7 MMTPA
Year 5 2.0 MMTPA
onwards
ii. Revenue share of 20% on gross revenue.