Steps to complete work along Amarnath yatra route

Image

Press Trust of India Srinagar

Chief Executive Officer (CEO) SASB Navin K Choudhary directed all the engineering staff and contractors to "mobilise additional manpower to the extent possible to complete the backlog work and put all infrastructures in time" for the commencement of the yatra on the schedule date, an official spokesman said.

The yatra is scheduled to begin on June 25 but inclement weather over the last few weeks has hampered necessary preparations, including clearance of tracks.

The CEO along with senior officials today visited Baltal base camp to take stock of the situation there and also inspected the track beyond Domel.

"It was observed that not only continuous bad weather has hampered the snow clearance work on the track but also delayed repair of other infrastructure like restoration of power, water supply and repair of huts," the spokesman said.

 

The CEO expressed satisfaction over restoration of the helipad and other structures which were damaged due to snow avalanches during last winter, the spokesman said.

  