BIA launch may be put off

| The commercial launch date of the new Bangalore International Airport (BIA) is likely to be deferred by two to three weeks from the scheduled date - March 28 - in view of the delay in the commissioning of the air traffic control (ATC) facility, the nerve centre of the airport. |
| A consensus to this effect was reached by the officials of the ministry of civil aviation and the directorate general of civil aviation (DGCA) at a meeting held in New Delhi on Monday to review BIA's preparedness to commence flight operations from March 28. |
| According to informed sources, the DGCA had expressed concern on several safety provisions including the incomplete ATC facility at the airport. A formal announcement on the postponement of the launch date is expected to be made on Tuesday. |
| With this, flights will continue to operate from the existing HAL airport. Sources said: "We discussed several issues pertaining to the facilities at the airport, one of the crucial component was the ATC. We have thought it fit not to hurry with the inauguration." |
| The move comes in the backdrop of the recent visit of a team of officials from the civil aviation ministry to BIA. The team had asked BIAL to ensure that the ATC facility was ready by March 20. |
| Sources said: "The personnel posted at the ATC need time to familiarise themselves with the equipment. They require training for at least a month on various equipment at the ATC facility. As the airport is expected to clock over 480 traffic movements per day, a study of the traffic pattern has to be conducted. Moreover, the ATC has to be kept on stand-by mode for a minimum of 1,000 hours before it is actually commissioned. However, these mandatory specifications cannot be met at BIA before the scheduled inaugural date." |
| Apart from the ATC facility, the civil aviation team had made another 58 observations regarding commencement of operations at the airport. |
| The postponement of the launch date will come as a respite to the state government, which has taken up several new infrastructure projects to improve road connectivity to the airport. |
| The Greater Bangalore City Corporation, which has taken up construction of ten underpasses to make the road to the airport a signal-free corridor, expects to complete work on at least five underpasses before the airport is thrown open to passenger traffic. |
| At present, one underpass has been completed and work on two are in progress. |
| Meanwhile, Rs 5 crore has been allotted in the state budget for 2008-09 as the state's initial equity in the new special purpose vehicle launched to undertake the work of providing high speed rail link to the airport. |
| "We will shortly decide as to who will execute the project," principal secretary (finance) M R Sreenivasamurthy said. |
More From This Section
Don't miss the most important news and views of the day. Get them on our Telegram channel
First Published: Mar 11 2008 | 12:00 AM IST

