Vehicular movement was suspended after cracks came up on a joint between two pillars of Iswar Gupta Setu, connecting Nadia with Hooghly district today.

Over 10,000 vehicles including motorcycle were diverted after PWD ordered closire of the bridge for indefinite period.

The cracks were first seen by rickshaw pullers who carry fishes early in the morning.

PWD Executive Engineer Saugata Sarkar said, "We have found flaws in a bearing on a pillar during preliminary inspection."

Inspection will take place at the joint of pillar and lower part of bridge which is possible only by reaching under the bridge.

Sarkar said bridge maintenance is a continuous process and there was no flaw in it.
 

"This was an abrupt development (cracks)," he added.

The defects were noticed at joint of P2 and P3 on the bridge.

Disclaimer: No Business Standard Journalist was involved in creation of this content

Don't miss the most important news and views of the day. Get them on our Telegram channel

First Published: Dec 17 2016 | 11:22 PM IST

Explore News