Bulk power buyers can choose supplier
Consumers will have to pay a surcharge to shift

| Bulk electricity users may soon have the option of changing their power distribution company on payment of a surcharge. | |
| A proposal mooted by a group of state regulators wants a formula based on 'avoided cost' and suggests compensation be paid to a distribution company if a bulk consumer shifts to another company. | |
| The compensation would have to be paid by the distribution company or discom to which the consumer proposes to shift. | |
| The proposal mooted for public debate suggests that the difference between the average tariff of a category of consumers and the cost avoided by the discom by buying less power to supply, will provide a measure of the surcharge. | |
| The move would enable open access in distribution for consumers who use 1 megawatt or more of electricity. The Electricity Act stipulates that a surcharge for the current level of cross-subsidy has to be specified by the state regulator and that consumers with a load of 1 Mw and above should have the option of moving to a supplier of their choice. | |
| The regulator will be required to estimate the projected capacity that is likely to move away due to open access. The migration will result in a discom having to purchase less power from marginal sources of supply. | |
| Hence, the weighted marginal cost of power purchase from such sources would be considered as 'avoided cost' for variable components of power purchase. | |
| Other charges, like applicable fixed charges of power purchase and applicable transmission and wheeling charges, will be added to the 'avoided cost' to arrive at the total cost of supply. | |
| The difference between the average realisation of a category and the 'avoided cost' of supply will be the cross-subsidy surcharge amount. | |
| The group considered four approaches to the surcharge issue. Average cost, embedded cost and marginal cost were found inappropriate. The 'avoided cost' concept was found suitable. | |
| The group also said that in view of the generation shortage, migration was not likely to result in any generation capacity getting stranded. | |
| In case of intra-state transmission lines and distribution systems, assets will continue to be used by the open access consumer by paying wheeling charges even after migration. | |
| If a situation of stranded generation or intra-state transmission and distribution assets does arise, the state regulator will have to settle the issue on a case-to-case basis.
| |
More From This Section
Don't miss the most important news and views of the day. Get them on our Telegram channel
First Published: Dec 23 2004 | 12:00 AM IST

