Robot lifts bits of melted fuel at Japan's Fukushima plant

AFP  |  Tokyo 

A robot arm has successfully picked up pebble-sized pieces of radioactive fuel at in a complex operation seen as key to clean-up efforts after the 2011 meltdown, officials said Thursday.

Operator Electric Power (TEPCO) on Wednesday sent down a remote-controlled probe to the melted fuel at the bottom of the plant's reactor 2, one of three that melted down after a massive earthquake and tsunami in March 2011.

It caught five small pieces of the fuel debris and lifted them up some five centimetres (two inches).

"We were able to confirm that the fuel debris can be moved," said Yuka Matsubara, a

"We accomplished the objective of this test," she told AFP, adding that the company plans to actually remove some fuel debris as a sample by March next year.

Robots have already peered inside the reactor to allow experts to assess the melted fuel visually, but Wednesday's test was the first attempt to work out how fragile the highly radioactive material is.

Removing the melted fuel is considered the most difficult part of the massive clean-up operation in the wake of the worst nuclear disaster since

It is not expected to begin until 2021, and has other issues to resolve including how to dispose of large quantities of contaminated stored in containers at the

The March 2011 tsunami that caused the meltdown was triggered by a massive undersea quake and killed around 18,000 people.

Tens of thousands were forced to evacuate their homes because of the threat of

Authorities have been working to rebuild the region, about 240 kilometres (150 miles) north of Tokyo, although areas near the crippled plant remain uninhabitable because of dangers.

(This story has not been edited by Business Standard staff and is auto-generated from a syndicated feed.)

First Published: Thu, February 14 2019. 15:35 IST